Hi all:
Does anyone remember how JFK's T4 operations were affected when the IAB was torn down and the new T4 was being built? Which gates did the airlines use? I assume at some point they had to move planes around, or split operations.
Thanks in advance.
mikephotos
2005-09-09, 05:56 PM
It was done in sections. Old "IAB" gates were used on one side while old gates/wings were torn down for rebuild on the other. Lots of hardstand/planemates activity during that period.
Mike
rod945
2005-09-22, 05:28 AM
It was done in sections. Old "IAB" gates were used on one side while old gates/wings were torn down for rebuild on the other. Lots of hardstand/planemates activity during that period.
Brilliant stuff whats it called? [^]
rod945
2005-09-22, 05:28 AM
It was done in sections. Old "IAB" gates were used on one side while old gates/wings were torn down for rebuild on the other. Lots of hardstand/planemates activity during that period.